News & Events

Ricardo Kramer a software developer in the Singletouch Calgary office realized an once-in-a-lifetime opportunity to carry the Olympic Torch more...

New Business Win
Congratulations to Studon Electric & Controls Inc., who have just been awarded a substantial contract for the Devon Jackfish 2 project in the Alberta oil sands.  Studon is a long standing customer of Singletouch and we are delighted the Singletouch project control system played a role in giving the project owner confidence. more...

 

 

 

 

Marty Hilsenteger CEO of Singletouch will speak about gaining operational efficiencies through technology adoption in a presentation titled “Are Outdated Business Processes Putting Your Entire Business at Risk?” at the Electric West Exposition & Conference at the Las Vegas Convention Center on Wednesday, March 17 from 2:30pm – 4:30pm, Session # W20. For more information visit the Singletouch booth # 706 on the exhibition floor March 15th- 18th

 

Singletouch recognized as one of the top New Products of the year

New Time and Attendance DemonstrationTime and Attendance

Singletouch exhibiting at the IEC Electric Expo

New CEO Video Message

Chemco contract announcement
Singletouch is proud to announce a new contract agreement with Chemco Electrical Contractors limited.
Click here for the full story.

Singletouch expansion, creating new vacancies across the globe.
See our careers page, for the latest job postings in the US, Canada and the UK

Singletouch explained in simple terms
Click here to read our latest press release which will take the mystery away from the question “how can an enterprise software system benefits your business’’

 

Labor Monitor Report 

The Labor Monitor report is just one of the reports generated by the Project Control module in Singletouch. The Project Control module allows organizations to:

- control costs
- understand percentage complete,
- update clients on the progress of the job in real-time
- report performance of jobs in the field.

The Labor Monitor report assists a Project Manager in managing the efficiency and productivity of his work force in the field. Starting on the left side of the report, the project manager can view the budgeted amounts based on costs code. When the budget is setup, the Project Manager will select all cost codes for the project and each cost code will have a materials, services, labor, subsistence and DJE budget amount ($) associated to it. In addition, each cost code will have the total number of hours of labor to complete that portion of the project.

The Labor Monitor report combines budget data, actual data (e.g. time tickets) and the field survey. The field survey allows the project manager to capture exactly which items have been installed onsite and through a simple calculation determines the percentage complete for that item. Typically, the field survey is done on a daily or weekly schedule which keeps the Labor Monitor report highly accurate and up to date.

This report aggregates the data which allows the Project Manager to:

- understand the percentage complete by cost code
- forecast labor hours to complete the cost code
- understand the productivity for each cost code.

In addition to hourly project statistics, the report also displays the same information in dollars.

In summary, the Labor Monitor report is a critical tool for project managers to understand what is truly happening on the ground and will enable the organization to accurately predict what is happening on a project and to have a confident informed discussion with the client prior to the end of the project.


Click the image above for a larger view

Labor Monitor Report Explained

The Labor Monitor Report contains both hourly and revenue information related to the progress and efficiency of an ongoing project. This report can used for a variety of purposes by a variety of roles within an organization. This document will describe the data contained within the report and explain the benefits of each element.

Cost Code
The report displays all cost codes selected in the Budget and all of the cost codes selected on time tickets within the Activity. This allows a manager to ensure that all items have been cost coded correctly. Cost codes are customized to suit the clients needs.

Original Budget CO Curr. Bgt.
The next three columns identify the budgeted number of hours for each cost code. The Original Budget column contains the hours for a specific cost code that have been loaded onto the project’s Original Budget. There can be multiple Original Budget’s for each project and the report would group these Original Budgets accordingly.

The CO column indicates the number of hours for a specific cost code loaded onto all change orders. If an Original Budget has 4 change orders, the CO column would indicate the total number of hours specified on all 4 change orders for that particular cost code.

Curr. Bgt. displays the sum of the Original Budget hours and Change Order hours for that cost code.

Comp. %
The Completion Percentage column pulls its values directly from the Field Survey. When the Field Survey is configured and used during the project, the manager will receive highly accurate percentage completion values for each cost code. This is because the Field Survey uses observed installed items to generate the Completion Percentage values.

Hrs. ATD
Time Tickets are entered in a variety of ways and all hours will be totalled by cost code in the Hrs. ATD (Actual to Date). This column will be updated each time the report is run so managers can get a handle on exactly the number of hours entered. This column forms the basis for the productivity calculation.

Earned
To calculate earned hours, we multiply the Current Budget hours by the Completion %. This will indicate how many hours have been earned on the project. This number may differ from the Actual hours to Date and it is this difference that helps generate the Forecast.

Forecast
The Forecast column indicates how many hours it will take to complete the job based on the Hours Actual to Date divided by the Percentage complete. The Forecast value is critical to plan resources with in order to correct the allocation of labor on a project.

Prod.
Productivity is likely the most important value in this report. At a glance a manager is able to evaluate the performance of the labor on a project by the Productivity. If the Productivity is over 1.0, the project is under budget and possible ahead of schedule. If the productivity is less than 1.0, the project is over budget and perhaps behind schedule.

Bgt. Total
Budget Total pulls its values directly from the Activity Budget for each cost code. The value displayed is the Labor portion of the budget only and does not include the budget for Materials, Services and Equipment.

Bgt. TD
Another way of saying Budget To Date is Earned Budget. This field will take into account the earned number of hours and display the Budget To Date in a financial way.

Rev. ATD
Similar to Hrs. ATD, the Revenue Actual To Date field sums all revenue related to completed time tickets for the project.

Variance
Variance represents the difference between the Budget To Date and Revenue Actual To Date columns to give a financial picture on the progress of the labor portion of the project. Similar to Forecast, this will assist project managers and stakeholders in adjusting expectations for the client.

Bgt. Rate Rate ATD
The Budgeted Rate represents the simple calculation of blended labor rate based on the hours and total revenue found in the budget. If the estimator took all roles into account when building the Budget, the Budgeted Rate would display the blended hourly charge-out rate for all employees.

The Rate Actual to Date value is calculated using actual time tickets and their cooresponding revenue in order to display the actual blended hourly labor charge-out rate for all employees.

These two fields assist in understanding if the project has the correct balance of roles. If the ratio of Journeymen to apprentices, for example, is wrong, these two columns will provide a way to check and balance the ratio.

For professionals managing a workforce, the Labor Monitor report provides the tools which will allow you to manage your workforce and your customer`s expectations.